Sometime after 9 p.m. on Ellin Road, a police officer or traffic-control worker stops cars at Hanson Oaks Drive for up to 15 minutes. A light-rail vehicle on a test run rolls through the intersection on the stretch between Annapolis Road and New Carrollton Station. Emerson Place is closed for the night. The testing window ends at 5 a.m.
The same thing happens every night along the Riverdale Park stretch between Veterans Parkway and College Park–UMD. Past 10 p.m. it moves through the campus segment out to Adelphi Road. For people living along this corridor, the Purple Line now behaves like a working railroad that keeps unusual hours. That changes what matters for the coming year. The crews putting down track are mostly finished. The trains running at night are what set the schedule now.
Construction Is 92% Done, and Testing Will Decide the Rest
In its September 3, 2026 update, the Maryland Transit Administration said construction was 92% complete. Light-rail testing was underway on more than half of the 16-mile line, in both Prince George's and Montgomery counties. The last piece of rail went in during May. In August, Hyattsville Wire reported that crews around Route 1 had moved on to repaving the streets and sidewalks they had torn up.
So when will riders board? At a recent Montgomery County Council committee meeting, reported by WTOP on October 5, Committee Chair Evan Glass asked about the opening date. MTA's Ray Biggs gave this answer:
"The contractual date does remain December 30, 2027."
Glass then asked whether April 2028 was more realistic. Biggs said the final date depends on safety testing and called the process "dynamic," explaining that "that can go either way." MTA has not adopted April 2028. That date came up as a question at a council meeting, and the official target is still December 30, 2027. Biggs's answer does make one thing clear, though. The schedule now depends on what the test trains show, and construction progress no longer drives it.
Where the Overnight Trains Run in Prince George's County
Here are the test windows on the Purple Line project's updates and detours page as of early October 2026. That page changes often, so treat this table as a snapshot.
| Segment | Testing hours | What happens on the street |
|---|---|---|
| Annapolis Road to New Carrollton Station | Nightly, 9 p.m. to 5 a.m. | Traffic holds of up to 15 minutes at Annapolis Road and Veterans Parkway, Veterans Parkway and Ellin Road, Ellin Road and Hanson Oaks Drive, and driveways along Ellin Road. Emerson Place at Ellin Road closes nightly. |
| Veterans Parkway (MD 410) to College Park–UMD | Nightly, 9 p.m. to 5 a.m. | Live-wire testing. Trains pass through intersections with police or traffic-control support. |
| College Park–UMD to Adelphi Road–UMGC–UMD | Nightly, 10 p.m. to 6 a.m. | Pedestrian crossings are managed, and there may be brief delays as trains pass. Emergency vehicle access stays open. |
There will be more testing, not less. Hyattsville Wire reported that end-to-end testing is planned for early 2027, with trains passing each other in both directions. MTA's fall community meetings include a preview of "the expansion of testing in 2027." Over the next year, expect to see light-rail cars more often, and in more places.
The Closures That Last as Long as Testing Does
Some road changes on the corridor are there for construction and will end when the work does. Others are there because of testing, and those can last much longer. Mixing the two up can throw off plans for a whole year.
These closures are tied to testing and operations:
- Glenridge Shopping Center entrance from Veterans Parkway. It will stay closed through construction and testing, which is expected to run through the end of 2027. The closure gives vehicles access to the Glenridge Operations and Maintenance Facility and allows the parking lot and intersection to be rebuilt. Use the entrances on Annapolis Road.
- Rittenhouse Street at Kenilworth Avenue. The crossing stays closed, so Rittenhouse Street is right-turn-only, to finish system installation and testing through fall 2026. The pedestrian crossing stays open.
- Emerson Place at Ellin Road. Closed every night during the New Carrollton test window.
These are on a construction schedule:
- Ellin Road, about October 19 to November 13, 2026. One lane in each direction between Hanson Oaks Drive and Emerson Place while track and systems are updated. Access to Alta New Carrollton is maintained. The rest of Ellin Road's current setup, closed between Harkins Road and Emerson Place and two-way from Emerson Place to Veterans Parkway, stays in place through the end of 2026.
- 66th Avenue at Riverdale Road. Closed through the end of 2026 while the intersection, curbs and sidewalks are rebuilt.
- Kenilworth Avenue (MD 201), River Road to East-West Highway. Work continues through fall 2026. All on-street parking has been removed, and the project page warns that parked vehicles will be towed at the owner's expense.
- Riverdale Road (MD 410), Baltimore-Washington Parkway to Veterans Parkway. Lanes are shifted north for construction of the Beacon Heights–East Pines Station, with two lanes kept in each direction.
The Glenridge entrance stands out. It is the one closure on this list scheduled to last about as long as the contractual opening date, and if testing moves the opening date, that closure could move with it.
On Campus, the Trains Will Start Running in Daylight
The University of Maryland's fall 2026 transportation guide says testing on campus runs on select nights this fall. Daytime testing is expected to start later in the academic year. When it does, trains will share the road with pedestrians, drivers and people on bikes and scooters. That affects anyone who drives through campus or walks around it, students or not.
The university's guidance is practical. In the core of campus the rails sit in the roadway, leaving a narrow gap that can catch a bike tire, scooter wheel or wheelchair caster. UMD advises crossing the tracks at a 90-degree angle instead of riding alongside them. Drivers are told not to stop on the tracks for deliveries, pickups or dropoffs. The overhead wires are live high-voltage lines, so keep ladders and tall objects away from them, and call 911 if one is down. UMD posts campus closures on its Purple Line construction and testing notices page.
Dates on the Fall Calendar for Prince George's Residents
MTA holds Community Advisory Team meetings to preview what testing comes next. The fall meetings are virtual, run on Microsoft Teams from 6 to 7:30 p.m., and offer captions in multiple languages. Three of them cover segments in Prince George's County, and one deadline matters for corridor businesses:
- Thursday, October 15: College Park meeting.
- Tuesday, October 20: University Boulevard meeting.
- Tuesday, October 27: Riverdale Park/New Carrollton meeting.
- November 7: Round 3 of the 2026 MDOT Purple Line Small Business Grant closes.
Since 2025, the grant program has given $3 million to 287 small businesses hit hardest by construction. MDOT calls it highly competitive and notes that not every eligible applicant will receive a grant. Lily's Nail Salon on University Boulevard East in Takoma Langley Crossroads was among the recent recipients, Source of the Spring reported in July. The meetings are also where MTA presents what testing comes next, and so far that has been the information that affects the corridor's schedule.
What Is Being Planned Around the Stations
The county is not waiting for opening day to plan what goes next to the stations. In May, the Prince George's County Economic Development Corporation reported that the Redevelopment Authority of Prince George's County had put out a request for proposals for about six acres of county-owned land at 6700 Riverdale Road. The site is right next to the future Beacon Heights–East Pines station. The county envisions mixed-income housing, neighborhood retail, commercial space and pedestrian-oriented public amenities, and the site is inside a federally designated Opportunity Zone. That is the same stretch of Riverdale Road where traffic has been shifted north for station construction.
Fares are partly settled. Biggs told the committee the line will take SmarTrip, CharmPass and cash, and officials hope to offer WMATA's tap-to-pay system by opening. In Prince George's County the line will stop at Takoma–Langley, Riggs Road, Adelphi Road–UMGC–UMD, Campus Drive–UMD, Baltimore Avenue–UMD, College Park–UMD, Riverdale Park North–UMD, Riverdale Park–Kenilworth, Beacon Heights–East Pines, Glenridge and New Carrollton. Test trains already run at night from New Carrollton to Adelphi Road, through most of them.
If you own a home near one of these stations and want to know how construction closures, testing timelines or a long project like the Beacon Heights–East Pines RFP could affect your plans to sell, rent or stay, I'm glad to go through it with you. I follow the Purple Line updates for Prince George's County and can help you sort out which changes are temporary and which will last. Reach out to A. Wise DMV REALTOR®. Let's Connect.